Btw was linked to this thread from other locked one by @@Bebo as this one is supposed to be hidden to guests?

 

But it seems to be on main forum

 

This one is meant to be public.

 

 

Looking at the wording of my post from where you were linked, i understand why you came to that conclusion. I'll reword it.

Link to comment

Update on the stadium last night:

 

PHASE 1

Ground works almost complete and will be finished by end of next week

Main contractor moves on site the week after to start work on the 5/6 football pitches and associated buildings, gym etc

Due for completion July 2019

Price of phase 1 has increased to £11.5m due to increased quality of pitches, undersoil heating and irrigation systems

 

PHASE 2

This is planned to begin in June/July 2019

Decision of the appeal is due May 2019

Cost of Stadium projected to be £45m

Link to comment

Pittodrie is our home. It has been a massive part of all our lives.

Enshrined in history. Situated within walking distance of the city centre, in the heart of our city. There's no other place like it.

 

Stopped reading there.

It’s an outdated, depressing, shit hole.

 

Nae aimed at you, just my general opinion.

  • Upvote 2
Link to comment

Update on the stadium last night:

 

PHASE 1

Ground works almost complete and will be finished by end of next week

Main contractor moves on site the week after to start work on the 5/6 football pitches and associated buildings, gym etc

Due for completion July 2019

Price of phase 1 has increased to £11.5m due to increased quality of pitches, undersoil heating and irrigation systems

 

PHASE 2

This is planned to begin in June/July 2019

Decision of the appeal is due May 2019

Cost of Stadium projected to be £45m

 

That makes it unaffordable then, going by the club's figures to rule out other options.

 

And it's not even what it will actually end up costing. 

 

Skimmed over the training ground cost too, so £56.5m so far.

Link to comment

That makes it unaffordable then, going by the club's figures to rule out other options.

 

And it's not even what it will actually end up costing. 

 

Skimmed over the training ground cost too, so £56.5m so far.

 

I think the final cost will be nearer £60m+ - the idea that you could have built all that for £40m in 2018-2021 is farcical.

Link to comment

That makes it unaffordable then, going by the club's figures to rule out other options.

 

And it's not even what it will actually end up costing. 

 

Skimmed over the training ground cost too, so £56.5m so far.

 

I think the final cost will be nearer £60m+ - the idea that you could have built all that for £40m in 2018-2021 is farcical.

Link to comment

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...